What actually drives the cost of building work
Why two quotations for the same extension differ so widely, which variables actually move a construction price, and how to compare quotes that are not comparable.
We do not publish prices. A construction figure quoted without seeing the building, the ground and the specification is a guess, and a guess that is wrong in your favour is the most expensive kind.
What is useful is knowing what moves the number. Once you can see the variables you can read three quotations and understand why they differ — which is usually not because one builder is greedy and another is generous.
The ground
Foundations are the single biggest source of variance on a domestic job, and the least visible. A standard trench fill on good ground is one price. Trees within influencing distance, made ground, a high water table, a drain in the way, or an old mine working underneath are all a different price and sometimes a different foundation type.
This is why we look at the ground before quoting rather than after. A contractor who quotes an extension without asking what is under it has either priced for the best case or left themselves room to come back to you.
Structure and spans
Removing a wall costs what the steel costs plus what holding the building up while it goes in costs. A 3-metre opening in a non-load-bearing partition and a 5-metre opening carrying the floor above are different jobs entirely.
Two things drive it: the span, and where the load goes when it arrives at the ends. A beam that lands on an existing pier is straightforward. A beam that needs a new padstone, a new pier, or its own foundation is not.
Glazing and roof
On a rear extension the glazing is frequently the largest single line in the quotation. The gap between a standard patio door and a large aluminium sliding system runs into five figures on its own, and it is entirely a specification choice.
Roof type matters similarly. A warm flat roof with a lantern, a pitched roof tied into the existing, and a flat roof with rooflights are three different costs before anyone talks about finishes.
Finish level
This is where the widest range sits and where quotations diverge most, because it is the easiest thing to leave vague. Sanitaryware, kitchen units, tiling, flooring, ironmongery and lighting can be specified across a range of several times over on the same footprint.
It is also the most controllable. A scope that fixes the shell and gives you a stated allowance for the finishes lets you decide later without reopening the contract.
Access and constraints
How material gets in and spoil gets out is a real cost. A terraced house with no side access means everything through the house or over the roof, and it changes the labour on every single delivery. A steep site, a shared drive, a narrow lane, a permit-only street, or a conservation area restriction on materials all price differently from the same job on an open plot.
Comparing quotations that are not comparable
Three quotations with a wide spread usually means three different scopes, not three different profit margins. Before comparing the totals, check they contain the same work.
What to check in each one
- Is the foundation type stated, or is it "assumed standard"?
- Are the structural steels priced, or subject to the engineer's design?
- Is building control included, and whose name is the application in?
- Are the finishes specified, or is there a stated allowance, or nothing at all?
- Is making good to the existing house included, and how far does it extend?
- Is scaffolding, skips, welfare and site clearance in the number?
- Is VAT stated, and is it in or out of the headline figure?
- What are the payment stages, and is anything due before work starts?
The cheapest quotation
A number well below the others is information. Sometimes it is a contractor with a quiet month. More often it is a scope that leaves things out, an optimistic foundation assumption, or a price that depends on variations later.
Ask what it excludes. A contractor who cannot answer that quickly has not thought about it, and it will be your problem in week six.
Where this comes from
Everything on this page was checked against the primary source in September 2026. Regulations, designations and thresholds change, and nothing here is a substitute for advice on your own property or contract. If you spot something that has moved, tell us and we will correct it.
Common questions
Questions on this
Why will you not give a price over the phone?
Because it would be wrong. The foundation design, the span, the glazing and the access all change the number materially and none of them can be established over the phone. We would rather visit, look, and give you a figure you can hold us to.
What is a reasonable contingency?
On work to an existing building, hold something back for what is found when it is opened up. Old houses contain surprises — no lintel over an opening, a drain where the drawing says there is not one, rot behind plaster. A contingency you do not spend is money you keep.
Should I pay a deposit?
A payment for materials ordered specifically for your job is normal. A large payment before anything happens is not. Payment should follow work done or materials delivered, in stages, and the stages should be in the written quotation before you sign anything.
Do prices change once work has started?
They change if the scope changes or if something is found that could not have been seen. That is what a variation is, and it should be priced and agreed in writing before it is built, not added to the final invoice.
Where this applies
The work this affects
- Home extensions Single and two-storey rear, side and wraparound extensions, from first survey to building control sign-off.
- Full house renovations Whole-property refurbishment — strip out, first fix, second fix and finishes under one contract.
- Kitchens & bathrooms Full replacement including the plumbing, electrics, tiling and making good afterwards.
Start a conversation about your project
Tell us what you are planning. We will come out, look at it properly, and put a written quotation in front of you.